JACBO realized a load-bearing and economical bored pile foundation for the new construction of a parking garage at Nuremberg Airport. After a pile test load and the determination of the embedment criterion, 565 bored piles with a diameter of 60 cm and lengths of up to 10 m were installed.
The design was carried out using piledesigner.io's powerful calculation engine to safely absorb vertical loads of up to 2.5 MN per column.
Thanks to efficient construction site logistics and high drilling performance, the project was completed within just five weeks - a reliable basis for the new parking garage construction at Nuremberg Airport.